SFS Intec

Burkey was hired as the general contractor to construct a 220′ x 120′ pre-engineered Butler building addition to the SFS Intec warehouse in Exeter Township.

The 26,400 square foot addition is 43′ high to accommodate a racking system.  The high racking system required the construction of a super-flat concrete floor, which was poured and finished to achieve an F-min 95 rating.

The building utilized an MR24 roof and included 16 skylights.  Additional Butler structural material was used to reinforce the existing building to accommodate the addition.  This project also included an “in-rack” sprinkler system.

Client:  SFS Intec

Design:  By Owner and Butler Manufacturing Co.

Cost:  $1,720,000

Burkey’s Role:   General Contractor